Over the past few years, data centres have become one of the key pillars of Malaysia’s digital economy, and their expansion is now driven largely by the computing needs of artificial intelligence (“AI”). Between 2021 and mid-2026, investments linked to data centres in Malaysia reached about RM385.7 billion.[1] In the first three months of 2026, the authorities approved 33 data centres and cloud computing projects with a combined value of RM34.6 billion[2].
This article analyses the two main incentives available to investors in AI data centres:
- 1. The Digital Ecosystem Acceleration (“DESAC”) Scheme; and
- 2. Malaysia Digital (“MD”) Tax Incentive.
The MD Tax Incentive is administered by the Malaysia Digital Economy Corporation (“MDEC”) and supports qualifying digital activities carried out by companies with MD status. The DESAC scheme is administered by the Malaysian Investment Development Authority (“MIDA”) and targets digital infrastructure.
- A. MD Tax Incentives Scheme
According to the Guidelines on Malaysia Digital Tax Incentive[3], a company that undertakes the research, development or commercialisation of solutions or provision of services, using any of the promoted technology enablers can apply for MD Tax Incentive. The list of promoted technology enablers is stated as follows:
- a. artificial intelligence or big data analytics;
- b. internet of things;
- c. cybersecurity;
- d. cloud;
- e. blockchain;
- f. drone technology;
- g. creative media technology including extended reality (XR) or mixed reality (MR);
- h. integrated circuit (IC) design with embedded software;
- i. robotics or automation; or
- j. advanced network connectivity or telecommunication technology.
Applications must be received by MDEC between 19.4.2024 and 31.12.2027 before the issuance of any sales invoice for the qualifying activity, subject to applicable exceptions.
- A1.Reduced Tax Rate (“RTR”) and Investment Tax Allowance (“ITA”)
The MD Tax Incentive has two categories, i.e. the New Investment Incentive and the Expansion Incentive.[4] Under either category, a qualifying company may choose either the RTR or the ITA[5].
The details of the RTR and the ITA[6] are summarised as follows:
|
No. |
Particulars |
RTR |
ITA |
|
1 |
Tax rate |
New Investment Incentive Non-IP income: 10% or 5% (subject to additional conditions)
IP income: 0%
Expansion Incentive IP and non-IP income: 15%
|
New Investment Incentive[7] 60% to 100% of qualifying capital expenditure (“QCE”)
Expansion Incentive 30% to 60%
|
|
2 |
Years of assessment (“YA”) |
5 to 10 consecutive YAs
|
5 years |
|
3 |
Commencement of tax |
Submit a request for the determination of the commencement year of assessment to MDEC no later than 24 months from the date of approval in principle. |
Starts when the company first incurs QCE after submitting its tax incentive ITA application. |
|
4 |
Employment conditions |
Maintain and/or employ an adequate number of full-time employees (“FTE”), including knowledge workers earning at least RM5,000 monthly basic salary. |
Maintain and/or employ adequate FTE to undertake the qualifying activity. |
|
5 |
Expenditure |
Adequate annual operating expenditure in Malaysia. |
Adequate QCE |
|
6 |
Maintenance of status |
New Investment Incentive: MD Status Expansion Incentive: MD or MSC Status |
|
|
7 |
Location of qualifying activity (“QA”) |
Undertake the QA in Malaysia at all times |
|
|
8 |
Economic development commitments |
Fulfil any other economic development commitments specified in the approval |
|
|
9 |
Annual compliance reporting |
Submit an independently verified self-declaration form to MDEC within 7 months after the end of each YA |
Not applicable |
|
10 |
IP income conditions |
Comply with the modified nexus approach to qualify for the respective IP rates |
Not applicable |
|
|
Additional Condition |
||
|
11 |
Sustainable economic development |
At least 2 to 3 additional conditions for lower tax rate |
At least 3 additional conditions in each of Years 4 and 5 to qualify for the higher ITA rate |
The MD ITA schedule for New Investment Incentive and Expansion Incentive are summarised as follows:
|
No. |
Conditions fulfilled |
New Investment Incentive |
Expansion Incentive |
|
1. |
Minimum conditions fulfilled within 36 months |
30% ITA on QCE incurred in the first ITA period |
30% ITA on QCE incurred in the first ITA period |
|
2. |
Minimum conditions maintained until the end of 5-year ITA period |
60% ITA on QCE incurred in both periods |
30% ITA on QCE incurred in both periods |
|
3. |
Minimum and additional conditions fulfilled before expiry |
100% ITA on QCE incurred in both periods |
60% ITA on QCE incurred in both periods |
- B. DESAC Scheme
According to the Guideline for DESAC Scheme[8], digital infrastructure providers carrying out either of the following qualifying activities may apply:
- a. Submarine cable including cable landing station; or
- b. Data centre and cloud computing/ data centre and data hosting.
Applications must be submitted to MIDA between 1.1.2022 and 31.12.2027, before the company issues its first sales invoice for the proposed project.
- B1. ITA & Special Tax Rate (“STR”)
Similarly, there are two incentives available under the DESAC Scheme, i.e. ITA and STR, which are summarised as follows:
|
Particulars |
New Company[9] |
Existing Company[10] |
|
|
ITA |
STR |
ITA |
|
|
Tier 1 (minimum and additional conditions) |
100% of QCE (excluding land) |
10% on statutory income (excluding IP income) |
60% of QCE (excluding land) |
|
Tier 2 (minimum conditions only) |
60% of QCE (excluding land) |
15% on statutory income (excluding IP income) |
30% of QCE (excluding land) |
|
Incentive period |
5 or 10 years |
5 or 10 years |
5 years |
|
Set-off against statutory income |
Up to 100% |
Not applicable |
Up to 70% |
A New Company only gets the second five years if it also meets the second-period conditions in B2 below.
- B2. Minimum and Additional Conditions
MIDA determines the tier in its approval letter. A company that fulfils both the minimum and additional conditions throughout the incentive period qualifies for Tier 1, while a company that fulfils only the minimum conditions qualifies for Tier 2. The key conditions[11] are summarised as follows:
|
Particulars |
New Company (ITA / STR) |
Existing Company (ITA) |
|
First 5 years |
||
|
Minimum Conditions (Tier 2) |
1. Paid-up capital of at least RM2.5 million 2. Capital expenditure incurred as proposed 3. Full-time Malaysian employees earning a minimum monthly basic salary of RM5,000 must represent at least 50% of total manpower 4. At least two local vendor development program 5. Adoption of Industry 4.0 elements 6. Adopt at least one green technology as proposed
|
|
|
Deadline to comply with minimum conditions from the date of principle approval letter until the expiry of the first 5 years
|
1. ITA: not later than 36 months 2. STR: not later than 24 months
from the date of the approval-in-principle letter, and to be maintained until the end of the first 5 years |
Within 36 months from the date of the approval-in-principle letter, and to be maintained until the end of the first 5 years |
|
Additional Conditions (Tier 1) |
1. Annual operational expenditure including domestic ancillary services as proposed
2. High Value Jobs
3. Undertake minimum three (3) local vendor development program
4. Appoint minimum one (1) local vendor
5. Collaboration with universities and technical institutions
6. Any other conditions related to the sustainable economy development such as education, social, accelerate Malaysian SMEs and as stated in the approval letter |
1. Capital expenditure (excluding land) of at least RM300 million for a period of 5 years
2. a) to f) of New Company ITA / STR additional conditions
Companies within the same group undertaking the same QA as their parent companies / related companies must operate from separate premises, use separate plant, machinery, equipment and employees (except management staff and directors), and must not reduce the investment of their parent or related companies.
|
|
Second 5 years |
||
|
Minimum Conditions (Tier 2) |
1. Compliance with all minimum and additional conditions imposed for the first five years;
2. Cumulative capital expenditure (excluding land) incurred at least RM1 billion;
3. Undertake minimum two (2) local vendor development program;
4. Substantial increase in number of full-time Malaysian employees with minimum monthly basic salary of RM5,000 where it represents at least 50% of total manpower.
|
Not applicable as the incentive period is 5 years. |
|
Additional Conditions (Tier 1) |
Same as the first 5 years |
Not applicable. |
Commentary
For investors in AI data centres, the choice of incentive is a commercial decision as much as a tax one. It should be made at the planning stage, not after the project has started. Both the DESAC Scheme and the MD Tax Incentive accept applications only until 31.12.2027. Both also require the application to be filed before the first sales invoice is issued. A company that waits until its facility is running may find that it no longer qualifies for either.
The two schemes reward different kinds of business.
- a) DESAC is built for companies that own and operate the physical infrastructure. Its value comes from heavy upfront spending on buildings, power systems, cooling and servers. A New Company that reaches Tier 1 can set an allowance of 100% of its QCE against all of its statutory income. In practice, this could shelter the profits of the early years almost entirely; and
- b) The MD Tax Incentive is aimed at businesses whose value lies in the services and technology they deliver, such as AI model development, cloud-based platforms and data analytics, rather than in the hardware. Its reduced rates, and the 0% rate on qualifying IP income, suit companies with lighter capital needs and income that is expected to grow.
Investors should also note that these incentives come with ongoing conditions rather than being one-off approvals. They include local employment and salary thresholds, local vendor development programmes, green technology commitments and, for data centres, the power and water efficiency benchmarks in the Guideline for Sustainable Development of Data Centre[12].
[1] https://www.mida.gov.my/media-release/mida-charts-next-phase-for-malaysias-data-centre-sector-from-attracting-investment-to-building-value-for-smes-and-malaysians/
[2] https://www.mida.gov.my/media-release/malaysia-attracts-rm92-8-billion-in-q1-2026-approved-investments-expected-to-create-over-50000-new-jobs-domestic-investments-up-13/
[3] https://www.mdec.my/md-documents/guidelines-on-malaysia-digital-md-tax-incentive–new-investmentjuly-2025
[4] A minimum paid-up capital of RM50,000 for New Investment Incentive or RM250,000 for Expansion Incentive.
[5] It must be noted that both RTR and ITA are mutually exclusive.
[6] Section 127(3)(b) of the ITA
[7]The applicable incentive rate and period are subject to the relevant eligibility requirements and fulfilment of the minimum and additional conditions.
[8] https://www.mida.gov.my/wp-content/uploads/2024/12/DESAC-Guideline_MIDA.pdf
[9] A company set up to undertake a qualifying activity which has no existing or related entity in Malaysia carrying on the same qualifying activity.
[10] A company already approved under the DESAC Scheme which undertakes an expansion project (in which case the incentive period for the expansion cannot exceed the remaining period of its existing incentive), or a company with a related entity in Malaysia approved under the DESAC or MSC/MD scheme for the same activity.
[11] Summarised from the DESAC Guideline. The conditions listed are not exhaustive, and MIDA may impose further conditions in the approval letter.
[12] https://www.mida.gov.my/wp-content/uploads/2024/12/Guideline-for-Sustainable-Development-of-Data-Centre.pdf
About the author
Yap Wen Hui
Senior Associate
Co-Head,
Tax, Customs and Incentives Practice Group
Halim Hong & Quek
wh.yap@hhq.com.my
Kelly Yeoh Xuan Jing
Paralegal
Tax, Customs and Incentives Practice Group
Halim Hong & Quek
kelly.yeoh@hhq.com.my